Cabling a Data Center to TIA-942 Standard
The Purpose of TIA-942 Standard
- The purpose of TIA-942 standard is to provide requirements and guidelines for the Design and Installation of a data center or computer room
- TIA-942 standard will enable design to be involved early in construction process
- TIA-942 allows for long term planning of data centers to support growth and future applications
TIA-942 includes guidelines for data center design, cabling system infrastructure, telecommunications spaces and topologies, cabling systems, cabling pathways, redundancy and informative annexes.
What is a Data Center?
Data center is a building or portion of a building whose primary function is to house a computer room and it’s support areas.
Types of Data Centers
- Private domain or enterprise data centers
- Public domain data centers
Data Center Design
Coordination of all aspects of a data center is critical including
- Telecommunications cabling system
- Equipment floor plan
- Electrical plans
- Architectural plan
- HVAC
- Security
- Lighting system
Recommended design process is
- Estimate needs at full capacity for all equipment
- Anticipate future growth over life of data center
- Provide all requirements to architects and engineers
- Create an equipment floor plan
- Design telecommunications cabling system
The following figure shows the relationship of spaces in a data center
Data Center Tiers
- Relates to levels of availability of infrastructure
- Tier Classifications were originally defined by The Uptime Institute
- Addresses critical systems of data center
- Critical systems may have different ratings
- Ratings can be degraded as data center load increases over time
Data Center Tier I – Basic
- Single path for power and cooling distribution
- No redundant components
- May not have a raised floor
- Susceptible to disruption from planned and unplanned activity
- 28.8 hours of annual downtime
Data Center Tier II – Redundant Components
- Single path for power and cooling distribution
- Redundant components
- Has a raised floor
- Slightly less susceptible to disruptions than Tier I
- 22.0 hours of annual downtime
Data Center Tier III – Concurrently Maintainable
- Multiple power and cooling distribution paths – only one active path
- Redundant components
- Allows for any planned site infrastructure activity without disrupting computer hardware operation
- 1.6 hours of annual downtime
Data Center Tier IV – Fault Tolerant
- Multiple active power and cooling distribution paths
- Redundant components
- All computer hardware must have dual power inputs
- Can sustain at least one worst-case, unplanned failure or event with no critical load impact
- 0.4 hours of annual downtime
TIA-942 defines the following critical systems
- Telecommunications
- Architectural and Structural
- Electrical
- Mechanical
Tier 1 Data Center Telecommunications Requirements
- Cabling, racks, cabinets & pathways meet TIA-942 requirements
- Has 1 entrance pathway from access provider to facility
- Single pathway for all cabling
- Recommended labeling per ANSI/TIA/EIA-606-A and Annex B
Tier 2 Data Center Telecommunications Requirements
- All requirements of Tier 1
- Has 2 entrance pathways from access provider to facility
- Routers & switches to have redundant power supplies and processors
- Addresses vulnerability of service entering building
Tier 3 Data Center Telecommunications Requirements
- All requirements of Tier 2
- Be served by at least 2 access providers
- A secondary entrance room
- Redundant backbone pathways
- Multiple routers and switches for redundancy
- Addresses vulnerability of a single access provider
Tier 4 Data Center Telecommunications Requirements
- All requirements of Tier 3
- Redundant backbone cabling
- Backbone cabling should be in conduit or have interlocking armor
- Optional secondary distribution area
- Optional redundant horizontal cabling
- Addresses any vulnerability of the cabling infrastructure
Telecommunications Spaces
- Entrance Room (ER)
- Main Distribution Area (MDA)
- Horizontal Distribution Area (HAD)
- Zone Distribution Area (ZDA)
- Equipment Distribution Area (EDA)
Entrance Room (ER)
- Access provider demarcation point
- Termination equipment for access provider cables
- Interface between data center cabling and inter-building cabling
- Pathways for all entrance cables
- May be located inside or outside computer room
Main Distribution Area (MDA)
- Central point of distribution
- Includes the main cross-connect (MC)
- May include horizontal cross-connect (HC)
- Core routers & switches for LAN/SAN, PBX are located here
- Located inside computer room
- Must be at least one MDA
Horizontal Distribution Area (HAD)
- Supports all the cabling to the equipment distribution areas
- Includes the horizontal cross-connect (HC)
- Switches for equipment in EDA located here
- Located inside computer room
- Minimum of one HAD per floor
Zone Distribution Area (ZDA)
- Optional inter-connection point within horizontal cabling
- Located between HAD and EDA
- Allows frequent reconfiguration and flexibility
- Should serve a maximum of 288 connections to avoid cable congestion
- Shall be no active equipment (except for DC power)
Equipment Distribution Area (EDA)
- Space for end equipment – servers, mainframes, tape drives
- Horizontal cabling is terminated here onto patch panels
- Point-to-point cabling between equipment is allowed
Recognized Cabling Media
- 100-Ohm twisted-pair cable
- 62.5/125um and 50/125um multimode fiber
- Single mode fiber
- 75 Ohm coaxial cable
- Various options for each media such as traditional field terminations and pre-terminated configurations
Horizontal Cabling Topology
Horizontal Cabling
- Cabling from HAD to EDA including horizontal cables, horizontal cross-connects, patch cords, optional consolidation point or zone outlet
- 100 meter maximum horizontal cable distance. Note that distance reduced if zone area cable uses.
Backbone Cabling Topology
Backbone Cabling
- Cabling between ER, MDA and HAD including backbone cables, main cross-connects, horizontal cross-connects, patch cords
- Shall allow network reconfigurations and future growth
Cabling Pathways
- Data centers shall adhere to ANSI/TIA-596-B specifications with exceptions noted in standard
- Cabling shall not be routed through public spaces unless enclosed in secure pathways
- Maintenance holes, pull boxes, splice boxes shall be locked and monitored
Cabling Pathways – Separation of Cabling
- Proper distances must be maintained between electrical and twisted pair cables
- Branch electrical circuits should be in watertight flexible metal conduit
- Feeder electrical circuits to power distribution units should be in solid metal conduit
- If using cable tray – Minimum of 12” between trays
Access Floors
- Allocate separate aisles for power and telecommunications cabling
- If not possible, then provide both horizontal and vertical separation
Cable Trays
- Fiber and copper cabling in trays should be separated.
- The benefits are to improve administration, minimize damage to smaller diameter cables.
- If possible, fiber should be on top of copper
Cabling Pathways – Entrance Room
- Should all be underground
- Each access provider should have at least one 4” conduit
- Shall meet ANSI/TIA-569-B
Cabling Pathways – Access Floors
- Cabling under floor shall be in ventilated cable trays
- Trays may be installed in multiple layers
- Trays shall have a maximum depth of 6”
- Access floor should use bolted stringer structure
- Plenum rated cable is typical – consult AHJ
Cabling Pathways – Overhead Cable Trays
- Trays may be installed in multiple layers
- Trays shall have a maximum depth of 6”
- In shared-tenant data center common spaces – solid bottom tray or minimum of 9 feet above finished floor.
- Tray should be supported from ceiling
Redundancy
- Reliability of telecommunications infrastructure needs to be increased. This is defined by Tier ratings
- Very common to have multiple Service Providers
- Entrance Pathways should be on opposite ends of building
- If secondary ER required, access provider equipment should be able to operate independently, 20 meters of separation, and separate fire protection zones.
Redundancy – Main Distribution Area
If secondary distribution required:
- Core routers and switches should be distributed
- Circuits should be split
- Separate fire protection zones
- Separate power distribution units
- Separate air conditioning systems
Infrastructure Redundancy
Redundancy – Backbone Cabling
- Protects against outage caused by damage
- Common to see additional cabling – MDA to HAD, HAD to HAD
- Cabling should be run along different routes
- If secondary distribution area – Not required HAD to HAD
Redundancy – Horizontal Cabling
- Cabling should be run along different routes
- Still must meet 100 meter maximum cable lengths
- Critical equipment can be supported by 2 HAD’s – Separate fire protection zone
Informative Annex B
Identification of Cabling Infrastructure
Data centers should adhere to ANSI/TIA/EIA-606-A with exceptions as noted in standard
Identification Scheme for Floor Space
- Floor space should track the data center grid
- Use two letters and two numeric digits to identify each 600mm x 600mm (2ft X 2ft) floor tile
- AA, AB, AC … AZ, BA, BB, BC .. and so on
Identification Scheme for Racks and Cabinets
- All racks and cabinets should be labeled front and back
- For rooms with access floors, each rack and cabinet to have a unique identifier based on floor tile coordinates
- If cabinet rests on more than one tile, the same corner of each cabinet can be used to identify the grid location. Example: front right corner.
- In data centers with multiple floors, the floor number should be added as a prefix to the cabinet number
- Example: A cabinet whose right front corner is at tile AJ05 on floor 2, will be named 2AJ05
Identification Scheme for Patch Panels
- Each panel to be labeled with an alpha character starting with A, B, C … Z etc. Starting from the top of the rack down
- Horizontal wire management panels do not count when determining patch panel position
Patch Panel Identifier
- Near end cabinet location and panel identifier to be followed by the far end cabinet location and panel identifier + port numbers
- Example: AJ05-A to AQ03-B Ports 1-24
Cable and Patch Cord Identifier
- Cables and patch cords should be labeled on both ends with the location of both ends of the cable
- Example of the near end cable label – AJ05-A01 / AQ03-B01
- Example of the far end cable label – AQ03-B01 / AJ05-A01